About

Schedule

The Environmental Impact Statement is expected be completed with a Record of Decision by mid-2020. The timeline for the project is estimated as follows:

  • Late Nov. 2018: Refinement of LPA
  • Dec. 2018: Project Kickoff Meeting
  • Late Dec. 2018: Develop STOPS Ridership
  • Late Jan. 2019: Scoping Meeting
  • Nov. 2018 - Oct. 2019: Development of DEIS
  • Oct. - Nov. 2019: Review of DEIS
  • Nov. 2018 - Jan. 2020: Develop Conceptual Engineering Plans
  • Nov. 2019 - Jan. 2020: Develop O&M Costs
  • Nov. 2019 - Jan. 2020: Develop Capital Costs
  • Dec. 2019 - Jan. 2020: Develop Local Revenue Evaluation
  • Jan. 2020: Publish DEIS
  • Jan. 2020 - Feb. 2020: Preliminary Project Evaluation
  • Mar. 2020 - May. 2020: Develop FEIS
  • May 2020: Develop Conceptual Design Package
  • June 2020: Publish FEIS
  • July. 2020: ROD

2020-2022

  • FTA Project Development

2022-2025

  • Final Design & Engineering

2026-2030

  • Construction

2030

  • Service begins